Accessibility location Hoek van Holland

Work will take place on Hoeksebaan from 17 March. The 5 phases, in which the entire foundation will be renewed, will last a total of 9 weeks. During phase 1, BVDER will be accessible from the motorway via the usual road, but after that, we will unfortunately be inconvenienced. Below is an image of the work area with our company indicated by the logo:

 The schedule is as follows

  • Phase 1 17 March to 23 March Location 1
  • Phase 2 March 24 – April 21 Location 1 + 2 + 3

  • Phase 3 April 22 – May 1 Location 3 + 4

  • Phase 4 May 1 – May 12 Location 4

Detours

  • Phase 2, Location 2 starting April 7: From the N223, we remain accessible via the service road and the roundabout. To return to the N223, you can use the diagonal road on our premises and the constructed bypass to reach the service road.

    Exception: On Tuesday, April 15, the entire roundabout will be closed. On this day, the constructed bypass and the diagonal road on our premises can be used from both directions.

  • Phase 3: During the day (6:00 AM – 6:00 PM), we are accessible via the service road and the roundabout is fully open again. At night, access is only possible via the N223 coming from the direction of Hoek van Holland (Location 1). This road will then be accessible for destination traffic only.

  • Phase 4: Location 1 is now fully open. We can be reached via the N220, Haakweg, and N223 (Location 1). To return, follow the same route.